The Grębów project and three further locations in development.

In development

Grębów — green hydrogen project with a planned capacity of 8 MW

We are preparing a PEM electrolysis installation in Grębów. We have developed the project documentation and obtained opinions from Wody Polskie, RDOŚ and Sanepid in the environmental procedure. The opinions indicate that a full environmental impact assessment is not required for the assessed scope. We continue work on the environmental decision, grid connection and further investment preparation.

Full project page and next milestones

Documents and milestones

Status as of the project update of 21 October 2026.

  1. Wody Polskie opinion

    4 August 2026

    Status
    Received in the environmental procedure. This is an opinion, not a water-law permit.
  2. RDOŚ opinion

    24 August 2026

    Status
    Received. Supports no full environmental impact assessment for the assessed scope.
  3. Sanepid opinion

    12 October 2026

    Status
    Received in the environmental procedure.
  4. Municipal environmental decision

    Status
    Outstanding.
  5. Grid connection

    Status
    Preliminary PGE indication of 8–10 MW availability. A 9 MW application package has been prepared for 8 MW PEM plus auxiliaries. Formal connection conditions remain outstanding.
  6. Land acquisition

    Status
    Outstanding.

Pipeline

Other locations

We are also developing three further locations, including a project with a planned capacity of 20 MW. Location details remain confidential at the current stage of preparation.

further locations in development
3
planned capacity of one of them
20 MW