Grębów: planned 8 MW green hydrogen project

We are preparing a PEM electrolysis installation in Grębów. We have developed the project documentation and obtained opinions from Wody Polskie, RDOŚ and Sanepid in the environmental procedure. Work continues on the environmental decision, grid connection and further investment preparation.

Status as of the project update of 21 October 2026. The project is in development; it is not built or operating. Images on project pages are illustrative renders unless captioned as photographs.

What has been achieved

Project documentation developed.

Wody Polskie opinion (4 August 2026), received in the environmental procedure. This is an opinion, not a water-law permit.

RDOŚ opinion (24 August 2026), supporting no full environmental impact assessment for the assessed scope.

Sanepid opinion (12 October 2026), received in the environmental procedure.

Preliminary PGE indication of 8–10 MW availability; a 9 MW application package prepared for 8 MW PEM plus auxiliaries.

What remains outstanding

Municipal environmental decision.

Formal grid connection conditions.

Land acquisition.

Further investment preparation, including financing and supply agreements.

Next milestones

Environmental decision.

Formal connection conditions.

Land acquisition.

Subsequent permitting and investment decisions.

Wider pipeline

We are also developing three further locations, including a project with a planned capacity of 20 MW. Location details remain confidential at the current stage of preparation.

When will the project produce hydrogen?

We do not publish a commissioning date. It depends on the outstanding decision, grid connection, land and financing steps.